During this project, our task was a floating equipment refit. The goal was that after the refit, the floating equipment could function as a concert stage, but it could also be converted back into the original floating equipment if needed.

Main characteristics

  • Type: Floating equipment
  • Operating zone: Inland waters, 2nd zone

Main dimensions

  • Length: 12,6 m
  • Beam: 9,75 m
  • Displacement: 112,1 t

Construction design

Welded steel structure

Main tasks completed

  • Conceptual planning and optimization of the modular pontoon arrangement
  • Optimizing the floating equipment for various operating conditions
  • Stability booklet
  • Longitudinal strength calculation
  • Approval documentation

Project participants